A large portion of the previous week was spent working on the design report, getting feedback, and improving upon the suggestions from the design presentation. Within the report, I focused a lot on refining and writing the Architecture and Principle of Operation and the System Implementation of the dance mat itself. Currently, I am still working on the design of the interior of the mat and keeping it thin, especially now that we are moving the speaker from it. Once that is done, I should have some detailed images to show that interior. The electronics themselves work fine, so integrating them and finishing the mat will be the focus.

I am behind on the design part as well as the assembly. But if everything works as planned right now, everything should be ready for demo day to test. Finally, the plans for this week are to quickly finish up the design and actually begin putting things together for testing and demo by demo day.