Progress:
This week, the team made meaningful progress toward locking the oscillator implementation. We now have a concrete schematic to build around, and the key device characterization data needed to support final design decisions has been compiled and reviewed. In particular, the NMOS measurement results were revisited in detail to compare Id, gm, and Vth across chips and patterns, which helped narrow the device choices and provide Charlie with the information needed to finalize values in the design and pending for fab.
On the hardware side, the testbench PCB design is effectively ready pending final pin assignment from the oscillator schematic. In addition, orders have already been placed for the PLCC28 chip holder and the backup PLCC28 through-hole to DIP-28 adapter to support initial bring-up. As a result, much of the supporting infrastructure for early testing is now in place, and the remaining dependency is primarily the finalization of the oscillator design itself.
Schedule/Updates:
Last week, the team was roughly two weeks behind schedule due to delays in locking the oscillator design. Since then, we have reduced that gap and are now closer to less than one week behind, assuming the design is finalized on Monday as planned. The key improvement is that the project has moved from a characterization and planning stage into a concrete implementation stage, with both the schematic direction and the supporting measurement data now largely in place.
At this point, the main remaining bottleneck is final design finalization and the transition into fabrication. Once the schematic and pin assignments are locked, the team is in a good position to move quickly on the remaining integration and bring-up steps. To continue reducing the schedule delay, the team’s focus is to finalize the design promptly and then execute quickly on the now-unblocked downstream tasks, since much of the supporting data and bring-up planning/infrastructure has already been completed in advance.
Upcoming Deliverables:
Next week, the team’s top priority is to finalize the oscillator design quickly and move into fabrication. Once the design is locked, the immediate next steps are fabrication and continue organizing the initial bring-up flow. Since the chip holder and backup adapter have already been ordered, the initial bring-up path is largely prepared; the team is now mainly waiting on final design completion and fabrication to proceed.