Christian’s Status Report for 2/7/26

This week I helped specify use case requirements for our project to ensure that our MVP is indeed viable, including tallying up the weight, price, and helping estimate the latency requirements to look towards how usable our product will be. In addition to this, I planned out our semester work schedule in the gantt chart, and recently edited it to account for our shifted work schedule.

Within the next week, I hope to have a rough draft of both the physical position to digital position conversion module and the 3D print housing CAD done. As long as I start on these two things this weekend, I should be on schedule.