Team Status Report for 3/19

Over the past week, our team has focused on finishing the PCB and software testing. We are falling a little behind schedule on the software side since we still do not have a working concept of the Arudino and Screen Control integration. As we wait for the PCB this week, this should be our main task. Additionally, since the PCB is taking a lot longer than advertised, we are a week behind on our soldering plan. Fortunately, our Gantt chart has ample slack time to work with for our current standing. Our updated schedule will have all of our plans shifted back by a week with the above tasks inserted into this upcoming week.