Team Status Report for 3/6/2021

This week we finalized our design and worked on creating our design review presentation. In creating the design presentation we finalized our system specification for the hardware and software sides of our presentation. We also specified how we were going to implement our design.

One of the risks we see on the software side is achieving the required accuracy levels. In order to do this we will preemptively begin working on our the training and allocating more time to it in order to achieve the accuracy we need.

On the hardware side the main risk we currently see is building a strong enough support base to hold up all our clothes. In order to mitigate this risk we have been looking into materials to build our base with and have been carefully planning the structure we are planning to use to ensure it can hold the weight.

Overall we are still on pace and are looking to present a good design review and get good feedback about our design.