Team Status Report: Week 11

Progress In week 11, as a team, the following objectives were done. Successfully delivered INTERIM DEMO: Pending feedback from Profs and TAs. Collected new IR Devices and populated it with the IR Database Fully tested functionality of turning on DingSun Audio Amp and Disco LED light remotely using WebApp LED Light Read more…

Team Status Report: Week 10

Progress In week 10, as a team, the following objectives were done. Collected new IR Devices and populated it with the IR Database Fully tested functionality of turning on Vizio TV and A/C remotely using WebApp Web App Successfully Deployed and Tested Mechanical Design: Rotating Base Design Done – Pending Read more…

Team Status Report: Week 9

Progress In week 9, as a team, the following objectives were done. Web App Successfully Deployed LIRC Database migrated to IR Man’s MongoDB database Web to IR Circuit Local Testing Done and Passed Raspberry Pi Motor Control Done Motor Controller Soldering Done OpenCV ran successfully locally Set up GPU instance Read more…