Previously Done With Team (Week 1 to Week 5):

  1. Gantt chart planned
  2. IR circuits built and worked
  3. Camera tested

Progress:

  1. Made sure LIRC module runs successfully on RPi
  2. Planned detailed computer vision pipeline with input output specified

Working On:

  1. Researching specific computer vision model to use

Planned

  1. Finish assigned parts in design document