Chris’s status report for 3/21/26

This week I was able to connect to the raspberry pi and get some preliminary code down for motor control, the camera has still not been set up and so the task of making the CV work on the actual physical system is still in play. Also the ML algorithm is pushed back a little now. I do not think this is a major issue as I started working on other parts in later weeks now due to the unset up hardware. I also started planning and working on the 3 boards for the software player who will interact with the hardware. Next week I want to have the CV fully down and working and have most of the ML algorithm done so that it will be functional in checkers and Sorry but not necessarily Chess yet. The week after will be finishing motor control and getting the communication between STM and raspberry pi set up.