What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).
This week I worked mainly on creating our final demo video. I worked on ensuring that all the hardware would work inside of the car as well as mounting all of the components. I also worked on editing all of the film that we recorded as well as voicing over explanations of the system. I also collected more test data and performed more testing and validation to update our results.
Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?
Our progress on the board is on schedule. We’ve completed all of our major goals and are just finishing up the final report.
What deliverables do you hope to complete in the next week?
We are planning on doing more testing as well as finishing up the final report.