Henry’s Status Report for 5/1/2021

This week I worked on:

  • Validation section of the final presentation. Wrote about validation on each component and system validation.
  • Software integrated. Integrated visualizer API with user interface (aka main). Some new issues were found during integration, which we are fixing right now.

For next week:

  • Work on the final video and final report, and post presentation.

I am on schedule.