Claire’s Status Update for 04/19
Schedule This week we are scheduled to work on integration. Progress This Week This week Maxine and I were able to integrate the gripper with the gantry. We then decided we wanted to get a head start on the design document and analysis. Since I was originally responsible for the motors, I took on stepper analysis for the 6 steppers we used in out system. This included how XY distance would be moved with each step, how a half-step might…