Xiran’s Status Report for 11/20

This past week, I finished implementing our output GUI. Below is a gif demonstrating the interface:

The user can upload the two output files (golden and actual) and see 1) graphed statistics about the test case and 2) which instruction, if any, failed plus the register dump comparison. We present these information in order to help the verification engineer better understand the tests being run and more quickly isolate bugs.

I am on schedule. Next week, I plan to implement the input GUI, which should be simpler since it involves less components, and also work on the final presentation slides. There are improvements I want to make to this output GUI (play around with layout and colors); I will come back to this at the end of the semester.

Happy early Thanksgiving!