Accomplishment of this week
- Mandatory Lab (4h)
- Presentation Technical Challenge, System Choice, Solution Approach (4h)
- Research Switch, LED, Battery (4h)
Schedule Update
- Unable to start schematics due to lack of parts order. Need to postpone the circuit design due to parts not available.
Next Week Plan
- Start Box Exterior Design (50%)
- Start schematics design for switch tail light (50%)