Davids Status Report for 3/14

What did you personally accomplish this week on the project?

I wrote more code for pico pwm encoding. Along with DJ, we worked with multimeter for a decent amount in tech spark to ensure it was working correctly. I then continued and wrote more code for specific bit sending, ie sending a sync and an entire packet following. I then spent a few hours in lab working through this and debugging to the point that it worked! I then spent some time drafting decoding code. Some photos of our lab progress should be in the team report.

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

I am ahead of schedule now. Getting the encoding software working is a main part of our project and a part that I thought could be subject to delays. Now that I am through this I (we) are in a very good state to get our entire integration complete in coming weeks.

What deliverables do you hope to complete in the next week?

Next week my main focus is debugging the decoding software. This will complete our IR  and encoding submodules which means all we have left in theory is integrating with LCD and V2T submodule. Hopefully the decoding goes relatively smoothly as well in which case we are in a very good spot!