Personal Accomplishments this Week
Work on the physical project was lighter this week due to class time being taken up by design presentations and ad the design report being due on Friday. For the design report I mainly worked in assisting both David and DJ on ideas and supporting them when they needed information about the intended hardware and such, and I also made a couple of the diagrams sin the report, and citing sources. We were also waiting on our RPi PICO boards to come in so some of my work was also limited in that regard, but we should be in a good place to hit the ground running when we get back.
On Schedule?
We are still on schedule with our updated plan and also personally on schedule with my individual tasks as well. I have also started thinking and researching more on how we are going to integrate all of the parts of our project for the final product, which I will continue to work on next week.
Next Week Deliverables
I am planning on helping DJ get the PICOs up and running and I would like to get some information transmission through IR working. As I mentioned earlier, I also want to get a draft of how we are going to integrate all of the electronics into an ergonomic and usable form factor so that we don’t lose the user experience in the search for functionality.