Team Status Report for 3/21/2026

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?

  • We have addressed the previous significant risks with the case, as we now have a hard case, hard flex case, and soft flex resin cases. We are now informed of the different vibration effects through these cases and are moving forward with creating soft flex resin cases.
  • The risks with the FPA processing accuracy are still existing, however we will be addressing these risks during the first two weeks of April as we will move forward with testing then
  • (This is from last week, but we still need to work on FPA integration) We will most likely encounter many bugs with setting up and initializing the AWS connection with our current app (i.e. setting correct permissions, ensuring proper libraries are added, etc.)
    • Contingency plan: We will reach out to TAs during mandatory lab time with strong experience in AWS if we encounter any significant blockers.

Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?

No changes were made to the system design. 

Provide an updated schedule if changes have occurred.

  • Since we were focused on fabricating the physical cases, we are still behind on integrating the FPA code onto our mobile app. We plan on finishing this up this weekend and early next week. 

Here’s a link to a folder containing all the photos for the case development.