Sun A’s Status Report for April 29th

What did you personally accomplish this week on the project? Give files orphotos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).

I am currently working with Katie and Lance to integrate our parts. With Katie, we are working on making sure that we correct the mistake we made in our initial fabrication attempt — one of the sides was a bit long and had to be cut down to be balanced. With Lance, I am helping him to make sure that his ardunio output is not generating random notes in the first few seconds (have not addressed this issue 100%).

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

The integration is definitely taking longer than expected but we are in a good place — working MVP.

What deliverables do you hope to complete in the next week?

finalizing the fabrication + integration.

Leave a Reply