Team Status Report for 4/22/23

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?

The main risk was not being able to connect to Bluetooth, since the majority of our stats were BT Communicated. However, we fixed that this week so now we just need to figure out how to coordinate stat-taking with the system. Right now we are just fine-tuning the coordination of each of the sensors with the system.

Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?

Currently, our design remains the same and on track, we just had to adjust the colors of the balls, so that the LiDAR can track properly.

Provide an updated schedule if changes have occurred.

Our schedule remains the same as the previous weeks.