What did you personally accomplish this week on the project? Give files or
photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).
This week, I finished testing the pressure sensors. They are able to differentiate between the low, medium, and high pressure that we want for our project. They are relatively accurate and work well for our project. We will be ordering them from Amazon in the next week after Nish and Lee test out the pressure sensors and see how they work for themselves.
Video of pressure sensors: https://drive.google.com/file/d/1XjYCct6e8iyqOXaQRiQNeGvuUmjMI3tv/view?usp=sharing
Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?
I think that we are on track. We are making significant progress and will have a working project by interim demo.
What deliverables do you hope to complete in the next week
Next week, I will focus on getting Kivy and OpenCV up and ready to go. On Monday, Nish and I will try to be able to open the camera and receive BLE information in our interface. If we don’t finish on Monday, we will use Wednesday as our buffer.