Team Status Report for May 1

This week we finished development and both started and ended our testing phase. Testing was conducted on Friday and Monday. This involved developing testing strategies, doing the tests while we were gathered in the same place, and then evaluating the results. We were happy to find that all tests passed based on our requirements!

We also finished preparing our final presentation, filling in the final test results and additionally including links to sample test data. Mitchell practiced giving the presentation to the group.

We started planning our final video this week as well. We outlined what we wanted to include in the video and drafted a script for the voiceover and the footage we want to capture.

At this point, since we’re focused on our final materials, our risks and scheduling constraints are passing into the rear view mirror. We’re on schedule with our work. Our main risk is that the second covid vaccine dose incapacitates two of our members who are getting it next week.

Leave a Reply

Your email address will not be published. Required fields are marked *