Updated Gantt Chart

Updated Gantt Chart Link

For our updated gantt chart, we have completed the task “Integration of RPi + Transcript + ML” half a week early so we are currently working on the task “Complete System Debugging / Testing”.  Our current “complete system” for the demo uses a computer as the intermediary server that handles the speaker ML and transcript streaming.  Ellen is working on some ML improvements for integration and testing at this time. After the demo Cambrea and Mitchell will start the migration to using the AWS Server instead of our local computer for the task “AWS Migration”.   For our latency testing and  standard testing we will complete these during week 12 and 13  after we have migrated to AWS.  We will start revising our final report the during week 11, and work on our final presentation and video during weeks 12-14.