30 March

Team: The team has made a lot of progress since we first started. Since we are pretty confident in our ability to make one motor arm work, we’re positive we can duplicate the system for all six faces of the cube. Our biggest hurdle as a team, is ensuring we Read more…

23 March

Team: For this week, the team met with the staff to figure out what was expected from us. We have been making fairly steady progress in all three major components of the project. We decided that if we could have one motor arm be able to read and input and Read more…

9 March

Team: With all our parts finally in house, the team is poised to make good progress the upcoming work week. Sam now has consistent lighting and can zero in on the correct HSV values we need to properly scan the cube. Lily has the foundation set for her solver. JT Read more…

2 March

Team: There are a few low risk items currently on the table. Firstly, the latest batch of orders has yet to arrive. We placed them February 20th, and with Amazon Prime shipping we expected all the items in by now. We’ll be following up with staff to ensure we can Read more…