March 23: Team Status Update

  • What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?

Philip not being able to completely finish his individual parts before April 1st. He will be focusing on getting the Jetson working and pause his current work on the app.

Jing not being able to achieve 95% accuracy rate for ML algorithm: look into changing the architecture to improve from the current 80%

  • Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?

Added a USB Hub to use with the Jetson. Otherwise, no changes to the design.

  • Provide an updated schedule if changes have occurred.

The current goal is to finish all individual parts by April 1st.