Israel’s Status Report For 12.9.23

Tasks completed

Completed installing the components on board and proceeded on testing, Finalized communication and integration with Hang for Advice polling and sending game state.  Troubleshooted Arduino code as well as photo resistors for each of the segments in our board, integrating buttons into the board.

Progress status

Made large progress as I needed to start fresh on board development 9×9. Became behind schedule and still slightly so as I expected to have the board perfected by Thursday.

Tasks to complete

Finalize the testing of our board: tweaking the threshold values and perfecting the game state interpretation. Also in the process of redeploying some components as short circuiting as made them faulty.