Bert’s status report 4/25

This week, I focused on completing final system integration and wrapping up the project. I finalized the memory mapper implementation and successfully integrated it with the rest of the system, ensuring correct interaction across CPU, PPU, and APU components. I validated this integration by testing multiple mapper configurations, including Mapper1 and Mapper2 games, confirming correct functionality and improved compatibility across different cartridges. In parallel, I began drafting the final report, documenting the system architecture, design decisions, and validation results.

As this is the final wrap-up phase, the remaining effort will be dedicated to completing the final report and ensuring all aspects of the system are clearly documented and ready for submission.