Caleb’s Status Report for 03/07/2026

Spring break was this week, as such, this report will encompass the week of 02/22/2026 as well. Components for both the primary and secondary coils have been received, as have the power components and some of the circuitry components. Though the rest of the circuitry components have been delivered, nobody was available to receive them. As such, the circuitry has not begun assembly yet unfortunately. This means I am personally behind schedule. I am not overly worried about this, however. Judging by the size of the circuitry and how it will be assembled, I estimate that I can complete it on Monday 03/09/2026, and that will leave time for thermal testing, which I hope to have completed by 03/14/2026.