What I personally accomplished this week:
I worked with justin and sean on navigation. To avoid reiteration, see their posts. I also looked into how we would actually set up our final test enviornment. We are hoping we get a 10×15 area, but will probably get a 10×10 area. Carboard boxes are fine, but we will need a ton of them, they will move pretty easily and their width will cut down on their effective area. Cardboard sheets have a lower profile, but will also move easily. What I am thinking of doing is just going down to techspark and getting wooden board to cut as walls. I can then make some triangle mounts to drill in to the boards, giving us a low profile and being sturdy. Regardless, our walls need to be 16 inches tall at the minimum.
Progress relative to schedule:
We are on schedule aside from running detection.
Deliverables for our final week:
Finish our final demo plans and rehearse
make the video
make the poster
construct the test area