Team Status Report for April 8

Having completed our interim demo, we believe we are on track to achieve our desired end-result for the final presentation. The most significant risk now would be being unable to complete building our booth for the demo. This however, should be a relatively straightforward process as Shizhen has figured out the laser cutting process that we will use to build our display cases. We will start work on this in the next 2 weeks to have the booth ready by demo day. Another risk is failing to display the oscilloscope plots in the web application seamlessly. Right now the user experience with the animated plots is not ideal as sometimes the plot can fail to display and the plot lacks interactivity. To mitigate the risk, we will attempt other methods to display the plots, such as using Scopy, if the problem cannot be solved.

No changes have been made to the design of our system and our schedule remains the same.