Erik Feldmann’s Status Report for 02/18/2023

This week was fairly productive for both me and my team. Having a full week back from Atlanta, our team was able to collaborate and determine which materials were best to be purchased. We came to a decision on the RFID scanner, the RFID chip, and our IMU. I personally submitted the purchase order for the IMU. We should be able to get our hands on these parts this week. I also spent some time checking out the LIDAR unit we were bestowed. We determined detection of a golf ball is viable within a few meters, and plan to start writing code this week. We also met with Professor Kim with our modified idea, which he approves of.

I believe we are on schedule as of right now. We need to do a fair bit of testing this upcoming week, as well as start work on the web application.

I hope to have the IMU, RFID chip, and scanner in hands this week and get solid testing done on each. I would also like more research to be done on our Web App, and start writing some code.

Leave a Reply

Your email address will not be published. Required fields are marked *