Xuan’s Status Report for 4/29/2023

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).

We started working on the final deadlines such as the poster. I also am in the middle of repairing and strengthening the glove since the wire of the middle finger’s flex sensor apparently broke off. I’m also assisting Gram and David in their testing and calibration of the glove so that it is as accurate as possible.

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

We should be on track as we’re continuing our testing phase.

What deliverables do you hope to complete in the next week?

This week, I hope to finish all the testing as well as the final deadlines