Xuan’s Status Report for 4/22/2023

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).

I didn’t anticipate having to resolder most of the flex sensors because it was too short. I initially soldered so the sensors would fit exactly on each finger of the glove, but it turns out that extra room was needed. I also switched from using a hard wire to a more flexible one. These were setbacks that occurred but fortunately were resolved in time. I was supposed to work on the battery circuit this week but this took a large amount of time.

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

Progress is slightly behind schedule due to this setback, but we should be on track as we’re continuing our testing phase.

What deliverables do you hope to complete in the next week?

This week, I finish integrating the battery into the glove and also plan to continue integration and run the tests that require an assembled glove.