What did you personally accomplish this week on the project? Give files or
photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).
We prepared the slides for the design presentation. We also started with the design report, although we didn’t make significant progress yet because the feedback came yesterday.
Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?
We are slightly behind because our Gantt chart didn’t take into account the significance of the design review process and spring break. We updated the Gantt chart in response. Also, one of our parts was missing because the wrong part was shipped, so we put in a request for that. I think the original chart also had extra time that could be shortened, so we edited that part too.
What deliverables do you hope to complete in the next week?
I hope to finish the design report and start assembling the hardware glove module when the missing part arrives.