Yun’s Status Report for 2/12

I personally worked on improving the proposal presentation slides, revising the schedule (Gantt chart), and doing more research on which software languages and tools to use for the implementations. We realized that each modular task was in larger pieces than we wanted; thus, I worked on making tasks more modular so that each task can be completed in about a week.

My team has been working on specifying details for design choices by considering which languages to use to meet latency requirements and how the user experience would be. I believe that the team is on track in accordance with the planned schedule now. However, it is early in the project, so I am planning to work ahead if time allows, so that we can have some buffer time in the future when unexpected situations that are not planned occur.

In the following week, I am planning to do some research on finding resources for outfit color matching, and ideate what kind of format we would want to store such data. In addition, if time allows, I will also be studying app development briefly.

Leave a Reply

Your email address will not be published. Required fields are marked *