Team Status Report for 4/16

With about two weeks coming up to the end of our project, we are working on finishing the final components. We previously had stated we got all the components working in sync, however, they were not the final version such as the controller and display of the web application. This week was spent on integration with a focus on how we are going to test components and our overall project. We asked for advice about testing during our weekly meeting with our advisor and began researching. We are currently on schedule as this is about time to start with the testing side of integration. This upcoming week, we will continue our integration by adding breath control to the communication chain.