This week all of my time was spent working on the project proposal. This included working on the presentation slides (specifically the Technical Challenges,  Solution Approach, Testing, and Task portions) and doing research/planning for parts that we’ll need once we begin the building phase of the project. So far, I’m on time with all of the preparatory work for the proposal presentation. For this upcoming week, I’ll be focusing on polishing up the presentation slides and preparing to begin work on the Design Presentation and Report by researching mechanical/hardware materials to complete our BOM as well as beginning working on our block diagram.