Team Status Report for 2/27

This week…

  • Refreshed code for project, e.i. opencv and raspberry pi
  • Prepared for the proposal project
  • Presented the proposal project
  • Reached out to out interviewee
  • Took photos of intersection for data set
  • organized photos for dataset

Status…

  • On time but need to order components next week

Changes to the system

  • None at the moment

Current risks and mitigations

  • if there should be an enable button for our device
  • distractions from other attributes of the intersection
  • how all our devices will fit in the headband

Jeanette’s Update for 2/27

This is week….

  • prepared our design presentation
  • presented our design presentation
  • reached out to our interviewee
  • reviewed raspberry pi code examples

Status…

  • On time

Next week…

  • look more extensively at code examples
  • order the components
  • interview a visually impaired person

Jeanette’s Status report for 2/20

This week’s completed items:

  • Worked on gantt chart for proposal presentation
  • Finished powerpoint for proposal presentation
  • Researched tools and materials to use toward the project
  • Updated Professor Sullivan and Ramshi about project works

Next week’s goals:

  • Reach out to visually impaired people and schedule interview
  • Order critical componentsRefresh Raspberry pi knowledge