This week we finalized assembly of Rev1, worked on interfacing with the BM83 Bluetooth module, and began development on the UI.

We will meet on Monday or Tuesday to discuss our project and adjust our schedule as needed, likely deciding to expend available slack time in the schedule and maybe cut some non-essential parts.

Next week we will finalize what we want to display at the interim demo, and discuss changes we want to make for Rev2, hoping to get that shipped as soon as possible. Work with the BM83 and UI will continue.