Team Status Report for 4/25

We have two weeks left before the end of the semester. At this point, most of our project is wrapping up, although we still have things to aim for. Each component of our project works individually, and 2/3 of the pieces are integrated. We are able to demonstrate that the inputs/outputs of each components match our expectations, and would flow as desired if integrated properly.

The final presentation is on Monday, and will be done by Akash. Accordingly, our group spent time this week running tests for our components,  working on the slide deck, and generating graphs to include in the powerpoint. We finalized our decision to move to the phase vocoder as well in consideration of the fact that the wavelet transform experienced greater loss and took longer to process music.

Before “demo day”, we have the following goals:

  • Finish testing, and possibly re-test components post-integration
  • Attempt to integrate the final two portions
  • Implement the -15/+10 BPM requirement for Song Selection
  • Create the Video
  • Final Report