Risks

No additional risks.

Changes

No changes.

Schedule

Embedded: Eric and Melodee will need to fix the one remaining firmware bug.

Tile Enclosures: Eric and Melodee will need to finish constructing all the tile enclosures.

Circuits: Eric and Melodee will need to finish soldering the remaining PCBs. Eric will need to create a master tile.

GUI/Interpreter: No additional changes.