Eric’s Status Update for 4/25/2020

Eric’s Status Update for 4/25/2020

What did you personally accomplish this week on the project? Give files or photos
that demonstrate your progress. Prove to the reader that you put sufficient effort into
the project over the course of the week (12+ hours).
Made 8 complete codeblox tiles.
Integrated with Aarohi’s code.
Found out that our firmware is fundamentally too slow and had to redo the communication layer to operate within timer interrupt handlers to ensure that deadlines would not be missed.
Spent sooooo many hours trying to debug the newest firmware.  Still working on getting it bug free.
Is your progress on schedule or behind? If you are behind, what actions will be
taken to catch up to the project schedule?
Behind schedule.  My schedule is entirely blocked by getting this code to work.  Once that happens, we can finish up the project.
What deliverables do you hope to complete in the next week?
Code working, master tile made, and as many slave tiles made as possible.