Week 10 Group Journal

What are the most significant risks that could jeopardize the success of the project?
We are having trouble importing some modules onto the raspberry pi and this seems to be the biggest risk right now, since everything else is coming together well.
How are these risks being managed? What contingency plans are ready?
We will spend extra time in lab and ask professors if this issue cannot be resolved.
Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?
No changes made this week.
Provide an updated schedule if changes have occurred.
No changes made this week