Author LucaPosted on April 27, 2024April 27, 2024No comment Team Status Report for 4/27

Team Status Report for 4/27

Current Risks: More problems arise upon integration of all project modules Catastrophic failure of a component or set of components before demo Damage to PCBs or Arduino’s during capacitor soldering … Read More “Team Status Report for 4/27”

Author LucaPosted on April 20, 2024April 21, 2024No comment Team Status Report for 4/20

Team Status Report for 4/20

Current Risks: Cables aren’t resilient enough and begins shearing. Debugging this would be very difficult as they are long cables. The arduino and other hardware doesn’t fit in the allotted … Read More “Team Status Report for 4/20”

Author aduraniPosted on April 6, 2024April 6, 2024No comment Team Status Report for 04/06

Team Status Report for 04/06

Significant Risks and Management Strategies: Our primary risks include technical challenges in integration, potential mechanical failures, and ensuring precise control over the moving parts. We are managing these risks through … Read More “Team Status Report for 04/06”

Author LucaPosted on March 29, 2024March 29, 2024No comment Team Status Report for 3/30

Team Status Report for 3/30

Current Risks: A significant number of soldered components are faulty on the PCB Arduino Ammeter does not work as we expect Interfacing the two arduino is not as straightforward as … Read More “Team Status Report for 3/30”

Author LucaPosted on March 23, 2024March 24, 2024No comment Team Status Report for 03/23

Team Status Report for 03/23

Current Risks: Motor control is not as straightforward as we think for H-belt design A significant number of soldered components are faulty on the PCB 3D Prints fail or are … Read More “Team Status Report for 03/23”

Author aduraniPosted on March 16, 2024March 17, 2024No comment Team Status Report for 3/16

Team Status Report for 3/16

Accomplishments Whole Team – Long Ethics Assignment! Anirud – Enhanced PCB design, incorporating an op-amp and feedback resistors, crucial for improved sensor accuracy. Shifted all components to the top layer … Read More “Team Status Report for 3/16”

Author LucaPosted on March 10, 2024March 10, 2024No comment Team Status Report for 3/09

Team Status Report for 3/09

Current Risks to the Project: PCBs take longer than anticipated to ship Motor speed is much more limited than expected Design Changes: As stated in Callum’s report, we will be … Read More “Team Status Report for 3/09”

Author LucaPosted on February 25, 2024No comment Team Status Report for 2/24

Team Status Report for 2/24

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready? Currently, the main risks are … Read More “Team Status Report for 2/24”

Author LucaPosted on February 16, 2024February 18, 2024No comment Team Status Report for 2/17

Team Status Report for 2/17

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready? We are spending a lot of … Read More “Team Status Report for 2/17”

Author LucaPosted on February 8, 2024February 11, 2024No comment Team Status Report for 2/10

Team Status Report for 2/10

Current Risks to the Project: Neither Magnetometers nor Hall-Effect Sensors will work: In the event that we cannot viably sense devices with any of the tested methods, we plan to … Read More “Team Status Report for 2/10”

Pages

  • Design Review
  • Final Project Documents
  • Project Summary
  • Proposal

Archives

  • April 2024
  • March 2024
  • February 2024

Meta

  • Log in
  • Entries RSS
  • Comments RSS
  • WordPress.org
Team A5: Chargin' Proudly powered by WordPress