This week, I was mainly concerned with ordering parts. I decided we will order the PVC parts from F.W. Webb Company as we will need around 25 ft. of piping and they sold it in this size range. Mid-week we received some feedback from our design presentation. I decided to alter our frame design a bit based on that feedback. Originally, we were thinking of preventing the frame from toppling by adding weight to the front. However, it is not too difficult to add avoid tipping by lengthening the side bars. Next week, I would like to get a functioning prototype of the frame assembled.