For this week I focused on fixing the chassis, updating mounting, and improving RESQube localization accuracy. For the chassis, I changed the orientation of the Jetson and reduced LiDAR height, allowing the full electronics stack to be properly mounted. In addition, I tested out solenoid dispensing of RESQubes to ensure they are applicable to our application. For the RESQube firmware, I also implemented CSI for the localization which has shown some initial good results on improving accuracy, namely in conditions with more interference for our RSSI values. For next week I hope to have this fully mapped out as well as the final presentation fully done and practiced. I also hope to continue integrating with he rest of the team and helping with their own testing so we can keep on the schedule as we are now.
Mehaan’s status report for 11/26
Earlier week I managed to successfully conduct dry runs with Nav2 and our frontier algorithm. I moved onto manual testing on Nav2 via CLI, which is when I realised our odometry code needed some tuning since there was a rightward angular drift. After fixing the tuning, I have been testing across HH1303 and HH 1307. I’m still seeing some issues with regards to the accuracy of the costmap being published, and I am actively working on debugging .
On the side, I also helped with remounting the LIDAR and jetson.
Coming week will just be testing across various layouts, and then publishing the map to the website, which will be straightforward.
Team Report for 11/21/2026
This week we focused more on integrating and preparing for the final presentation. For integration, we made significant progress in the chassis for the RESQ rover, finishing the mounting for the Jetson, LiDAR, Camera, and sensor stack. The routing for wires was done also but might see changes leading up to our final demo. In addition, RESQube dispensing with the solenoid was tested and shown to be reliable, with our test matrix results showing a >95% dispensing success for various conditions and <1% failure on mis-dispensing.

For the RESQubes, CSI was implemented and changed the algorithm to a more robust victim localization. The new algorithm uses a weighted probabilistic criteria to better reject outliers during fetch of RSSI values. This is initially showing us better results but a full test with integration remains.
For our implementation of SLAM, we were able to find a good amount of success setting up the environment and integrating the Pico’s firmware to publish velocity commands to Nav2. In our tests we were able to see this work firsthand. To this end we are aiming to finish the tuning of drift and the continuous publishing of commands.
For some risks that we have some concern is in the updated victim localization where we are unsure if the fixes get us to our desired accuracy. A back up for our localization using packet timing is in our reserve and can be easily swapped out at detriment to agnostic victim hardware.
While some tasks remain slightly behind schedule, the team is generally on track with the current Gantt chart. We plan to have our presentation and tests for full run throughs done by next week.
Raghav Srinivasan’s Status Report for 11/21/2026
This week I mainly conducted rover maintenance and operations to assist with testing. For rover maintenance, the signal wire to the relay snapped off mid operation, so I resoldered it and resecured it in a manner that was more sturdy. Then, I assisted in securing the solenoid to the 3D print manufactured and designed by Ishaan. With regard to testing assistance, I assisted Ishaan with testing the RESQUBE dropping mechanism, and assisted with post processing the 3D print for the RESQUBE holder. Additionally, I monitored and diagnosed issues in testing with pico odometry, tailscale operations, and VNC issues that were blocking development.
Team’s Status Report for 11/14
This week, the team made significant progress on rover integration, RESQUBE localization, and resolving previous hardware issues. The rover’s CAD models were updated to accommodate the new chassis and replacement components, and the RESQUBE deployment solenoid was successfully integrated and tested. Previous I2C interference and Jetson–Pico serial communication issues were also resolved through electrical isolation and the addition of a flyback diode. On the sensing side, the new RPLIDAR A1M8 was successfully assembled and tested, demonstrating reliable obstacle detection at distances exceeding 2 meters through ROS2 on the Jetson. Due to faulty stereoscopic cameras, the team transitioned to USB cameras and successfully established a live feed to the base station. Independent tests of odometry and frontier exploration were also successful.
On the RESQUBE side, firmware and telemetry reporting were improved, and Channel State Information (CSI) was incorporated to evaluate RSSI measurement confidence and improve probabilistic victim localization. However, issues remain with multi-hop mesh communication, particularly when transmitting the Jetson-hosted web interface across two hops. Overall, integration is progressing well, and the team has recovered some time lost to hardware failures and component delays. While some tasks remain slightly behind schedule, the team is generally on track with the current Gantt chart. Next week, we plan to integrate LiDAR with autonomous navigation and base station mapping, improve mesh reliability and localization accuracy, and begin full-system testing of the integrated rover and RESQUBE network.
Ishaan’s Status Report for 11/14
This week, I primarily focused on integration of our rover, updating the RESQube firmware, and fixes to our previous communication architecture. For integration, I updated the CADs to fully fit our new chassis and new parts. Due to failures in some of our systems we had to change out certain components which required adjustments. The implemented mounts are pictures below.




In addition to this, I fixed and updated some for the telemetry reporting from the RESQubes and improved the algorithm for localization. This involved implementing Channel State Information (CSI) to validate the certainty of each RSSI measurement and create a probabilistic state estimator for a best confidence localization to be reported to the victims. In addition to this, on the fixes one of the implemented solutions, namely isolating our I2C lines, fixed the Jetson – Pico serial communication. Integration is overall going well and we are better on our schedule than last week. For next week I hope to have a more accurate and tested RESQube mesh and begin full system tests with the rest of the team.
Mehaan’s status report for 11/14
This week, I worked on integrating rover’s sensors with the Jetson. We finally got the RPLIDAR A1, and ran successful independent tests on it. Since both stereoscopic cameras from the ECE inventory turned out to be faulty, we are just going to use USB cameras along with our LIDAR readings. I brought up the USB cameras, and connected their live feed to the base station. Overall progress is slightly behind schedule due to faulty hardware and delivery related issues. However, independent tests of odometry, LIDAR and frontier exploration are successful. Next week, I plan to integrate the new LIDAR with our navigation software for autonomous exploration on the rover, and then move on to integrating it with the Base station for map generation.
Raghav Srinivasan’s Status Report for 11/14/2026
This week, I continued integration of subsystems with the rover, as well as the setup of new sensors. With integration, I built, tested, and integrated a system for actuating the solenoid that will be used to deploy RESQUBEs. Since the solenoid required 12V, I connected it to a relay that is actuated off the Pico. In testing conditions, with the rover fully sealed, actuating the relay caused issues with the I2C data lines, freezing the Pico. Root cause analysis revealed back EMF spikes were corrupting either the data or clock lines, and the issue was resolved via a reverse polarized diode, and retested. Reliability has been ensured. With new sensor setup, the LiDAR arrived, and it was assembled, with a wire harness soldered on, and electrically isolated. It was then tested on a Windows OS device, isolated from the rest of the rover. In those tests, it excelled, detecting placed obstacles and walls at ranges exceeding 2 meters. Additionally, when connected to the Jetson, the same results were achieved in ROS2, and visualized using rviz. Integration is progressing well. We are on track with the current Gantt chart. With regards to todo items, we need to fix issues with the speed and reliability of website packet transmission across the mesh network, as, when we tried to transmit the web interface hosted on the Jetson across the mesh, it was unable to be picked up on a phone browser after two hops, but worked fine after one hop.
Ishaan’s status report for 11/7
This week I focused on the mesh network, RSSI localization, and integration of the rover’s subsystems primarily. For the mesh network I discovered some architectural flaws with grandchildren in the mesh network not being recognized properly and acting like victims, which I corrected. With the architectural updates to the mesh network software I also included more quality of life changes for diagnostic and telemetry readings that should make debugging in the future easier. In addition to this I implemented internode communication so the mesh can communicate with both victims, other nodes, and the operator’s tablet. For victim localization I fully implemented and tuned the localization to work, as well as worked on validating and benchmarking it. For the current software & hardware implementation we were able to guarantee a localization accuracy of 1 meter to 5 meters. An action plan was also made to increase accuracy for this localization involving telemetry and map data. For integrating the rover’s subsystems, I primarily focused on debugging the Pico to Jetson communication link, which I narrowed down to a failure in the IMU’s I2C where we see it dump garbage data and cause the pico to hang. We are currently narrowing this fault down to ensure we can still operate the rover’s movement on the upcoming interim demo. Besides this I also worked on the CAD for the rover’s chassis, finishing and testing the last pieces that are compatible with what we have. For things to be completed for the next status report, ideally the Pico – Jetson link will be fixed or amended in some way and new solutions to localization will be prototyped. I am currently slightly behind schedule on the integration solely because of delays in our orders that are out of our control, but we are ahead on other areas, primarily software integration.
Mehaan’s status report for 11/7
This week I was able to start integrating and testing the software on the jetson. I set up the ROS environment on the Jetson and successfully tested SLAM toolbox and NAV2 in simulation. I also setup the L515 lidar, and was able to pass objet detection and accuracy tests. When testing the rover’s motor controls on the jetson we ran into some communication issues, which we are working on debugging. Overall, I am on schedule with hardware integration well underway. After all rover systems work well, I plan to move towards connecting the firefighter base station with the rest of the network.
