Cary’s Status Report for 9/28/2024

Accomplishments This Week: This week, I focused on updating the design of the remote controller for the project. I developed and finalized detailed schematics, capturing the design from multiple viewpoints to ensure clarity and thoroughness. I made significant progress in decision-making, finalizing all aspects except for the method to simulate weight, which remains under discussion.

Progress Evaluation: My progress is on schedule, with no significant delays. Although we changed the design of the remote controller a lot, I am moving steadily toward the next project milestones.

Next Week’s Deliverables: For the upcoming week, I plan to start the ordering process with the TA for the decided components. Additionally, I will compile a comprehensive list of material sources available, ensuring that everything necessary for the next phase of the project is accounted for.

This will help maintain the project timeline and ensure steady progress.

Check the new diagram:

https://drive.google.com/file/d/1eYKGII9tAvMpuPOwXikJ_ms9G_d58fbl/view?usp=drive_link

Leave a Reply

Your email address will not be published. Required fields are marked *