What did you personally accomplish this week on the project?
This week, I primarily spent time closing off some loose ends, and providing input for the group’s final presentation.
Regarding the group’s final presentation, I collected the necessary data to show that our code met all of the latency goals we set out to achieve in presentations 1 and 2. I additionally provided assistance in structuring the presentation, and gave feedback on how to improve it.
I additionally made a few fixes regarding the implementation of authentication on the webserver, and added a simple, pre-inference version of image pruning to the webserver to cut down on the number of useless images saved to the database.
Is your progress on schedule or behind? If you are behind, what actions will be
taken to catch up to the project schedule?
I believe my progress is still on-schedule. Next week should be enough to finish my part in the final submissions.
What deliverables do you hope to complete in the next week?
In this following week, I will be doing what I can to solidify our webserver implementation so that everything works as planned in the demo, taking additional measurements that will hopefully provide convincing information for viewers, and generally working on the necessary reports, videos, posters, and presentations due throughout next week.