Focused mainly on preparing and finalizing the final presentation, since I was the one presenting. I also started working on the final poster early to make sure we stay on track and don’t fall behind. In addition, I helped finalize testing across all subsystems and the overall system to ensure everything is validated.
Physical assembly is slightly behind schedule. To address this, we will prioritize assembly tasks this week and ensure more time is allocated specifically to completing the hardware integration.
Plan to continue working on and finalize the poster, and help push physical assembly to completion for the demo day. Also, aim to support any remaining system-level testing once the full assembly is complete.