The most significant risks that could jeopardize the success of our project right now is falling behind. The contingency plan for this risk is to make sure we hold each other accountable on our scheduled tasks. This week, we made some changes to our hardware component of the NVIDIA Jetson. After further research, we found that due to the power constraints, we found that the Raspberry Pi board to be more suitable for our project. There was no inherent cost of changing this component as all we had to do was request a new part with the staff. No updates to the schedule have occurred.