Team Status Report for March 18

Currently, our most significant risk would be the integration of the induced voltage measurements into our database. In the upcoming weeks, we will be working on getting the Arduino data into our web application under the specified latency limit. We have tested the Arduino sample gathering timing, which appears to be under 1 ms per sample. The remaining part of the latency would be to send the data to a SQLite database and have our web app gather that data from the database itself.

As of now, no changes have been made to our existing design of the system and the schedule remains intact. In the following 2 weeks, we will finalize our experiments by soldering them such that they are ready to be presented in the booth. By then, the web app framework will also be prepared such that we can start adding content to it in the following weeks.