Anita’s Status Report for 3/25

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours). 

This week was admittedly a bit of a slow week. However because I picked up the pace last week, there was quite a bit of slack time that I could lean on. 

I first ramped up on Kelly’s code. While there are not too many lines of code to ramp up on, the lines of code were very dense and took a fair bit of research on what each method did. I then designed what would be the interface between the feedback and pitch detection algorithm, and coded a portion of it up.

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule? 

Even though this week was chill, I’m still on track/ahead of schedule.

What deliverables do you hope to complete in the next week? 

I am to finish the interface in preparation for the tech demo next week.



Leave a Reply